On this commercial property, according to the contract terms, our company was required to work during the nighttime, as eyewear Lens Crafters operated from 8 am to 8 pm. By 8 am, all premises had to be cleaned and ready to receive staff and clients. Our tasks included sanding the walls, priming them, and applying two coats of paint. We also painted the ceiling frame and vents, removed the old carpet and hardwood floors, installed quartz vinyl tile floors in the main office, and carpeted the other three rooms. In addition, we had to remove and replace old baseboards in all rooms, paint trim and door frames on five interior doors, and restore office furniture. The challenge was to coordinate the work of simultaneously working electricians and ensure there was no interference. The time allotted for repairs was 7 working nights. ... Read More
On the first night, we removed some of the carpet, filled the space with self-leveling concrete leveler, and while it dried, we removed the old baseboards and patched cracks and nail holes in the walls. After the concrete leveler had dried, quartz vinyl tiles were laid on the floor. The challenge was the labor-intensive process of removing the carpets, which required careful planning of time and effort. Our company successfully completed the task, and the office opened on time in the morning.
On the second night, we sanded the walls and primed everything with Sherwin Williams quick-drying primer, with a drying time of about 1 hour. After drying, the first coat of paint was applied.
On the third night, since the owner planned to place expensive and delicate equipment in two rooms, we had to change plans. We focused on removing and installing carpet in these areas to ensure the equipment could be installed in the morning.
On the fourth night, we painted the ceiling frame, removed most of the carpeting in the main office, poured self-leveling concrete leveler, and when it was dry, installed quartz vinyl tile on the floor.
On the fifth night, the remaining carpet in the main office hallway and third room was removed, self-leveling concrete was poured, and the remaining floor in the main office was covered with quartz vinyl tiles. Additionally, the furniture was restored.
On the sixth night, the main office hallway floor was covered with quartz vinyl tiles, the third room was carpeted, baseboards were installed in all rooms, and the walls were given a second coat of paint. The baseboards also received their first coat of paint.
On the seventh night, the baseboards were given a second coat of paint, the door trims and door frames of the five interior doors were painted with Sherwin Williams ProClassic Interior acrylic enamel in two coats, and the quartz vinyl tile floors were given a final scrub to remove any adhesive residue. After a thorough inspection, the final touches were made. The project was completed within the agreed time frame, and the office opened on time in the morning.
Over the course of seven nights, eyeglass frames, glasses, display cases, equipment, office furniture, and official documents were carefully covered with protective film. At the beginning of each working day, construction waste and materials were removed, general cleaning was carried out, protective film was removed, furniture and office equipment were arranged. The office opened on time every morning.
The owner of Lens Crafters, a company that sells frames and installs lenses, was pleased with the work of our company. Read Less ...